Planning, Design & Construction

Advertisements (Current, Upcoming, and Recent)

Combined Design/Bid/Build Projects

The following is a list of Design/Bid/Build projects bidding together. Click for project information.

Project Name (Project#) Prebid Meeting Date Bid Open Date Pre-Bid
Attendance
General Site - Research Commons Thermal Plant (CP200001)
General Site - Utility Infrastructure for USDA Facility (CP220771)
Laboratory Animal Center - Building Demolition (CP229011)
12/01/2022
9:00 AM
Gen. Serv. Bldg. 194A
Non-mandatory
12/15/2022
1:30 PM

Request for Qualifications

Project Name (Project#) Submission Deadline
None at this time.

Design/Bid/Build

The following is a list of construction projects out for bid. Click for project information.

Project Name (Project#) Prebid Meeting Date Bid Open Date
No Projects currently out for Bid.

Design/Bid/Build Projects for Prequalified Health Care Contractors

Click here for a list of the General Contractors that have been prequalified for the following projects:

Project Name (Project#) Prebid Meeting Date Bid Open Date
No Projects currently out for Bid.

Design/Build Proposals

The following is a list of Design/Build projects. Click for project information.

Project Name (Project#) Mandatory
Pre-proposal
Conference
Submission
Deadline
None at this time

Construction Manager at Risk

The following is a list of Construction Manager at Risk projects out for bid.

Project Name (Project#) Electronic
Submission
Due Date
SOM-Renovate Laboratories on Multiple Floors RFQ (CP221461)
University of Missouri - Columbia, Missouri
12/01/2022 1:30 pm CST
MPC Infrastructure and ED Observation REnovation - RFQ (CP230481)
University of Missouri - Columbia, Missouri
12/02/2022 1:30 pm CST

Recently Opened Bids

The following is a list of bid projects opened in the last 30 days. Awarded contracts will appear in the "Recently Awarded Contracts" section

Project Name (Project #) Date
Bid
Opened
Bid
Tabulation
Power Plant — Replace Three Motorized Vehicle Drive Gates (CP221871) 11/15/2022
Patient Care Tower — Radiology Expansion (CP221611) 11/10/2022
Mizzou Student Athletic Training Facility Complex — Football Practice Field 1 & 2 Field Lights (CP222681) 11/3/2022
University Physicians Medical Building — 4th Floor Renovation (CP221944) 11/1/2022

Recently Awarded Contracts

The following is a list of recently awarded construction projects.

Project Name (Project #) Date
Contract
Awarded
Contract Awarded To Amount Awarded
Mizzou Student Athletic Training Facility Complex — Football Practice Field 1 & 2 Field Lights (CP222681) 11/11/2022 Kaiser Electric of Central Missouri, LLC $1,295,000.00
University Physicians Medical Building — 4th Floor Renovation (CP221944) 11/10/2022 Reinhardt Construction, LLC $1,499,400.00
Mizzou North — Demolition (CP219078) 10/19/2022 SIRCAL CONTRACTING, INC. $3,607,000.00
University Physicians Medical Building — Ground Floor CHCC Clinic Renovation (CP221951) 10/11/2022 BROWN & ROOT INDUSTRIAL SERVICES, LLC $610,000.00
East Campus Chiller Plant — Install Water Cooled Chiller (CP212233) 10/07/2022 ENVIRONMENTAL ENGINEERING, INC. $569,900.00

Projects in Design

The following is a list of future construction projects.

Project Number, Title, and Scope
Est. Ad
Date
Est. Bid
Open
Date
Various Locations - Roof Replacements (CP230161) E&G Roofs FY23 (Gentry, Hatch, Whitten, Strickland) (Replace Metal Roof System on Eckles Hall Under CP230162) Base Estimate & Alternates: $722,900.00 12/01/2022 12/20/2022
Lowry Hall - Renovate First Floor (CP220811) Reconfigure and renovate approximately 3,000 gsf on the first floor of Lowry Hall to create a new academic advising center for the College of Arts & Science. Base Estimate & Alternates: $923,744.77 12/06/2022 01/10/2023
Hulston Hall - Replace Fire Alarm System (CP221071) Replace Fire Alarm System - Hulston Hall Base Estimate & Alternates: $260,031.00 12/12/2022
Lewis and Clark Halls - Replace Fire Alarm System (CP221081) Replace Fire Alarm System in both buildings Base Estimate & Alternates: $331,336.00 12/12/2022
McReynolds Hall - Replace Fire Alarm System (CP221091) Replace Fire Alarm System - McReynolds Hall Base Estimate & Alternates: $106,936.00 12/12/2022
Various Locations - Generator Exhaust Modifications at PCT & UPMB (CP221501) PCT - Extension of Existing Generator Exhaust Stack from 15' to 25' & Delete Rain-cap to prevent CHF generator exhaust from being drawn into outside air intakes on PCT. UPMB - Addition of Special Plasma Air Filter on North Side Air-Intake (Receptor 29 in CPP Study) to prevent exhaust from being taken in by UPMB air intake locations. Base Estimate & Alternates: TBD 01/02/2023 01/16/2023
Various Locations - Metal Roof Repairs and Replacements (CP230162) Metal Roof Replacements at Rock Quarry Surplus Warehouse and Eckles Hall. Base Estimate & Alternates: $1,631,364.00 01/12/2023 01/31/2023
General Site - Replace Water Lines Near South Well (CP230191) Replace water lines North and East of GSB. Replace water main serving South Well. Base Estimate & Alternates: $504,913.00 01/12/2023 02/14/2023
Agriculture Science Building - Renovate Rms 2-6 & 2-7 (CP221711) Renovate both rooms to create modern teaching environment. Rm 2-6 to remain a sloped floor room with fixed seating similar to previous renovations. Rm 2-7 (smaller room), renovate to a flat floor classroom with a new teaching/seating layout. Base Estimate & Alternates: $429,487.50 01/13/2023 02/10/2023
Pershing Hall - Renovation for MU Student Health Center and SOM/MUHC Offices (CP221531) Pershing Commons has been identified to undertake a new role and comprehensive renovation to accommodate the Student Health Center on the Second Floor in an area of approximately 18,340gsf, and Faculty/Staff Offices on the First Floor in an area of approximately 13,830gsf to serve the School of Medicine and MU Health Care needs. Base Estimate & Alternates: $6,045,000.00 01/16/2023 02/21/2023
Student Recreation Center - Create Outdoor Fitness Center (CP222871) Completely remove the existing outdoor pool ( Truman's Pond). This project request entails complete demolition of the existing outdoor pool, compacting the soil, backfilling, intall drainage layer, concrete pad while working with contractors and vendors in creating a new design that will allow for an outdoor functional fitness space for our students. Base Estimate & Alternates: $1,455,470.00 01/16/2023 02/10/2023
General Site - Replace Utility Lines East of Memorial Student Union (CP230201) Replace Utility Lines East of Memorial Union Base Estimate & Alternates: $1,392,066.71 01/16/2023 02/21/2023
NextGen Precision Health Building - Level 4 - Shell Space Fitout (CP220972) Renovate approximately 33,000 square feet of shell space on the 4th floor of the Roy Blunt NextGen Precision Health Building for use as lab and office space. Base Estimate & Alternates: $12,370,704.00 01/19/2023 03/02/2023
Neff Hall - Building Envelope Repairs (CP220931) Neff Hall Building Envelope Repairs will consist of removal of the existing windows and installation of new aluminum windows with solid surface sills. The scope will address masonry repairs, tuckpointing and generalized cleaning. Additionally, the project will include the replacement of the existing front steps. Base Estimate & Alternates: $1,937,510.00 01/25/2023 02/15/2023
Telecommunications Center - Replace Existing Boiler (CP230471) Replace existing 1970 boiler in mechanical room of Telecommunications Building with lightly-used relocated boiler from another building. Base Estimate & Alternates: TBD 01/27/2023
Lottes Health Sciences Library - Renovation for Consolidation (CP211852) Renovation to approximately 38,000 square feet of Lottes Health Sciences Library to accommodate new medical science faculty offices and to provide a consolidated and modern Health Science Library space. Base Estimate & Alternates: $5,872,797.00 02/02/2023 03/02/2023
University Physicians Medical Building - 3rd Floor Renovation (CP221943) Design and renovate Third Floor for Pediatric Neurology, Pediatric Surgery/ENT/Urology and MFM clinic relocations. Base Estimate & Alternates: $2,638,850.00 02/06/2023 03/09/2023
General Site - Replace Steam and Condensate Line in Rollins Betwwem Virginia Ave. and College (CP230181) Replace 12" steam and 6" Condensate Line on Rollins, Virginia to College Ave Base Estimate & Alternates: $1,003,600.00 02/06/2023 03/10/2023
Southwest Center - Construct a New Cattle Handling Facility (CP230751) Construction of a cattle handling facility pole barn that will encompass a cattle handling facility and a calving area. Project will be a pole barn with a concrete floor comprised of basic electrical, plumbing and heating within the cattle handling portion. Facility to include a small entrance, single ADA uni-sex bathroom with an electric space heater. Within the cattle handing area, there will be a chute, pens and tubs needed as part of the facilities operation. The calving facility will be an unfinished area with dirt floors and wall protection and basic lighting. UPDATE: An addition of constriction of two (2) offices within another building on the Southwest Center's complex is being added onto the project. This office will consist of two (2) standard offices added into the assembly area. This was submitted under project CP231331 but is being incorporated into this project scope of work and construction timeline to utilize the same design consultants and construction administration. Base Estimate & Alternates: $255,500.00 02/15/2023 03/29/2023
Dalton Cardiovascular Research Center - Replace Electrical Panels (CP221051) Replace all original Federal Pacific Electrical panels. Base Estimate & Alternates: $853,192.77 02/16/2023 03/02/2023
Rock Quarry Surplus Warehouse - Paving Replacement (CP221442) Replace paving at Rock Quarry Surplus Warehouse Base Estimate & Alternates: TBD 02/24/2023 03/16/2023
Trowbridge Center - Electrical Service Entrance Panels Replacement (CP221141) Electrical Service Entrance Panels Replacement Base Estimate & Alternates: $344,852.31 02/28/2023 03/13/2023
Power Plant - Brick and Mortar Repairs (CP230671) Brick and Mortar repairs for the Power Plant l 970's Boiler buildings as outlined in CPI92092 Power Plant Brick Study. Base Estimate & Alternates: TBD 03/01/2023 03/22/2023
Tucker Hall - Various Renovations 5/5a, 201/202, 225 (CP231161) Room 5a add a bench and shelf on back wall (see specs) and all sockets would need to be connected to the backup power supply. Room 5 all benches will need regular power supply and a dishwasher installed We will need to replace old benches and shelving utilizing the original footprint 202, 202a, 202b Split Room 225 by building floating wall, adding door and making this room into two. Base Estimate & Alternates: TBD 03/02/2023
Hill Hall - Replace AHU and Fire Alarm Systems (CP222891) Replace the Air Handling Systems and Fire alarm systems in this building in association with CP220951. Base Estimate & Alternates: $4,710,000.00 03/09/2023
Strickland Hall - Electrical Service Panel Replacement (CP221111) Electrical Service Panel Replacement Base Estimate & Alternates: TBD 03/13/2023 03/27/2023
Power Plant - Replace Turbine 6 with Turbine 10 (CP211571) Replace existing Steam Turbine Generator #6, with a more efficient a more efficient turbine generator with a capacity of roughly 8MW. The Turbine will be furnished by MU and installed by the contractor. Base Estimate & Alternates: $2,525,303.00 03/14/2023 04/18/2023
Children's Hospital Facility - Parking Lot CG1-NE Reconfiguration (CP210045) Restore and reconfigure the northeast portion of Parking Lot CG1 taken off-line in 2019 to serve initially as construction staging for the NextGen project and then subsequently transferred to serve as construction staging for the New Children's Hospital Facility project, and increase the original 179 space capacity up to approximately 300 spaces. This project was identified as a Tier 1 priority in the recent CP210043 Southeast Gateway - Parking & Traffic Study report dated May 12, 2022, prepared by the Lochmueller/Walker traffic and parking consultant team. The goal is to have the parking lot operational by June 2024. Base Estimate & Alternates: $1,458,000.00 04/03/2023 04/27/2023
MU Research Reactor - West Building Addition (CP211941) Construct a 43,000 GSF addition to the west side of MURR to house offices for staff currently located in trailers and 15,000 GSF of shell space for future fit out of hot cells and laboratories. Base Estimate & Alternates: $14,780,727.00 04/13/2023 05/18/2023
Animal Science Research Center - Replace Electrical Service Entrance Panels (CP221041) Replace electrical Service Entrance Panels Base Estimate & Alternates: $1,236,384.00 05/10/2023 05/24/2023
Missouri Psychiatric Center - Infrastructure and ED Observation Renovation (CP230481) IDue to continued growth of emergency department volume, MU Health Care has identified a need to add sixteen (16) Emergency Department rooms to support future volume projections. Volume projections indicate an anticipated total of 99,698 visits annually by FY27, equating to a need for 77 total ED rooms. The proposed project meets this goal by providing 16 additional ED beds along with enabling infrastructure. The new 16 beds would be in the central portion of MPC 1st floor, adjacent and with direct access to the existing Emergency Department. The infrastructure component of the project entails a new rooftop air handling unit and generator and was originally planned as a separate project. Supply chain delays have greatly impacted lead times (55 weeks for AHU and 70 weeks for generator), thus shifting the construction timeline and making it now parallel to the 16-bed expansion project. As a result, it is recommended that these two projects be combined to streamline schedule, mitigate risk, and lower cost. Proposed Improvements: The project will renovate approximately 7,750 SF of the central portion of the 1st Floor of MPC building, to increase the ED by 16 beds including procedure space, support space and a centralized work station. This project will add incremental bds to accommodate an upward trending need for hospital emergency services. renovations that will accommodate an upward trending need for hospital emergency services. The proposed project scope also includes code required infrastructure upgrades as well as improvements to medical gas, domestic water distribution systems, and chilled water pumps. A new generator and Emergency Power System included in the infrastructure upgrade meets requirements for a critical care hospital. Base Estimate & Alternates: $6,375,000.00 07/13/2023 08/10/2023
Medical Science Building - Renovate Laboratories on Multiple Floors (CP221461) Renovate Laboratories on Multiple Floors Base Estimate & Alternates: $32,940,000.00 07/27/2023 08/24/2023
South Farm Swine Research & Education Facility - Construct Addition (CP230851) Construct an addition to the Swine Research Facility at South Farm. The existing building is approximately 14,000 gross square feet and comprised primarily of animal holding space. Base Estimate & Alternates: TBD 09/13/2023 10/11/2023
Memorial Student Union - Masonry Restoration Phase II (CP222801) Phase II of the restoration of the masonry for Memorial Student Union. Restoration will focus on the South Wing of Memorial Union. Base Estimate & Alternates: TBD 12/08/2023 02/08/2024
Swine Research and Resource Center - Construct Addition (CP230841) Construct an expansion of 12,220 gross square feet to the National Swine Research and Resource Center (NSRRC), a research animal housing and breeding facility. Base Estimate & Alternates: TBD 10/31/2024 11/29/2023

Disclosure: This list is intended for information purposes only. This is not a complete list, nor is the information provided guaranteed to be correct. Stated dates are subject to change.

Design/Bid/Build Projects for Prequalified Health Care Contractors in Design

The following is a list of future construction projects.

Project Number, Title, and Scope
Est. Ad
Date
Est. Bid
Open
Date
Patient Care Tower - Pharmacy Renovation T0020-T0039 (CP210781) Design to renovate existing pharmacy and adjacent spaces to accommodate additional carousel and IV hoods. Base Estimate & Alternates: $3,020,000.00 01/12/2023 02/14/2023

Disclosure: This list is intended for information purposes only. This is not a complete list, nor is the information provided guaranteed to be correct. Stated dates are subject to change.

MCA (Master Construction Agreement) Projects in Design

The following is a list of projects being made available through Nabholz. If you are interested in any of these projects, please contact Mitchell Fuemmeler with Nabholz at mitchell.fuemmeler@nabholz.com.

Project Number, Title, and Scope
Est. Ad
Date
Clydesdale Hall - A134 Renovation (CP221971) Renovating Rm A134 in order to move Physical Rehab department from A250. New flooring, lighting and doorway. Move/Install existing water treadmill in A250 Base Estimate & Alternates: $130,377.25 11/10/2022
Critical Care Addition - C2008D Nuclear Medicine - Imaging Equipment Replacement (CP220852) Imaging Equipment Replacement requested by Jeff Fleenor Base Estimate & Alternates: $247,191.00 11/22/2022
Hospital and Clinics Various Locations - CHF Supporting Infrastructure (CP221491) C-DAS Pathway into CCA from PCT - Necessary to connect the C-DAS of New CHF back to existing primary University Hospital infrastructure. PCT - P-tube System Upgrade Initiative & Infrastructure Preparation - This is a necessary separate project that needs initiated to provide the power, data, and pathways/provisions to accommod the SwissLog vendor equipment installation under a separate PO. Base Estimate & Alternates: $240,224.00 11/22/2022
Memorial Student Union - Repair Bell Tower Clock and Bell Components (CP211961) Repair and restore clocks on Memorial Student Union Tower. Install digital actuation system for bells. Base Estimate & Alternates: $158,000.00 11/29/2022
Rock Quarry Center Warehouse - Suite Q180 Renovation (CP230021) Renovation of Suite Q180 (approx. 4,000 sq.ft.) at Rock Quarry Center building. Includes primarily new interiors, including carpet, wallcovering removal and patch/paint, furniture, added walls for room divisions, HVAC and lighting repair as needed, and IT/card access upgrades. Base Estimate & Alternates: $162,174.27 11/29/2022
Clydesdale Hall - Prep B124 for Equine Standing CT (CP222001) Modifications to Room B124 in Clydesdale Hall for the installation of a Equine standing CT, including installing new door location, electrical modifications, new ethernet connection. The equipment also requires the construction of a new floor pit. Base Estimate & Alternates: $211,383.00 11/30/2022
Patient Care Tower - T3220C OR25 Light Boom Replacement (CP221821) Design only for the replacement of existing Skytron light booms with Stryker light boom. Base Estimate & Alternates: $107,228.00 12/08/2022
Missouri Orthopedic Institute - OR2 Light Boom Replacement (CP222291) Design only to replace existing one point boom system with 2 or 3 point boom system. Design will estimate construction costs to be used for funding approval for full project in FY23. Base Estimate & Alternates: $215,477.20 12/08/2022
Physics Building - Modify Laboratory for Walk-in Fume Hood (CP222451) This project will renovate room 33 on the ground floor of the Physics Building for a research laboratory specifically designed for the startup of new Assistant Prof. Andrew Meng. The new laboratory will be outfitted with a new 8' walk in fume hood including retrofits for new exhaust fan on the roof and associated duct work, plumbing, and room configuration modifications. Specific laboratory equipment items will be pre-purchased and installed. The project will be delivered via MU's Master Construction Agreement. Base Estimate & Alternates: $735,237.00 12/20/2022
Parking Structure - Virginia Avenue - MUPD & MU LS Temporary Relocation (CP220513) Temporarily relocate MUPD and MU Landscape Services during Virginia Ave Parking Structure Repairs. The relocation of the MUPD will involve a renovation of the basement of the General Services Building to provide a functional space for MUPD operations. The project will encompass several early releases for long-lead material and demolition to provide a white-box for construction. Base Estimate & Alternates: $875,000.00 01/03/2023
NextGen Precision Health Building - Install Medical Gas System in Outpatient Area (CP220971) Medical grade gas needs to be installed in the outpatient area of NextGen for compliance with DNV/CMS requirements. The existing Lab gas system does not meet the code requirements for medical use. This project number will be delivered as a Change Order to CP190721 (design by Burns & McDonnell (amendment), constructed by Whiting Turner(Change order)) Base Estimate & Alternates: $419,246.82 01/06/2023
NextGen Precision Health Building - Fitout Rm 1331 and Extend Liquid Nitrogen Lines (CP230291) Renovation to approximately1,000 square feet in the first floor of the Roy Blunt NextGen Precision Health Building for the creation of two separate research suites to be constructed in two phases. The first phase will include the extension of liquid nitrogen lines from the existing building system to three separate areas. Base Estimate & Alternates: TBD 01/23/2023
Schweitzer Hall - Renovate Various Labs (CP222651) Renovation to four existing lab spaces (Rooms 11, 14, 16 & 24) in the basement of Schweitzer Hall Base Estimate & Alternates: $560,151.00 01/26/2023
Graves-Chapple Meeting & Education Facility - Build Standard Machine Shed (CP230491) Construct a 4,800 square foot Machine Shed, pole barn construction, for the storage of farm equipment. This structure will occasionally be used as a pavilion for outdoor events held at the facility. Base Estimate & Alternates: $294,000.00 02/02/2023
Medical Science Building - Replace 208V Substation (CP221061) Medical Science Building - Replace 208V Substation Base Estimate & Alternates: $428,625.79 02/09/2023
Ellis Library - Rms 4 & 5 Paint, Flooring and Lighting (CP230411) Rooms 4 and 5 and the north/south hallway and east/west hallway: Remove fluorescent light boxes from drop ceilings (drop ceilings are being removed from Rooms 4 and 5). Room 5 and the two hallway: Install new black track lighting. Room 4: Reinstall existing black track lighting after suspended ceiling is removed. Rooms 4 and 5: Build a double-wide doorway (no doors) between 4 & 5, near east side of rooms 1) Room 5: install carpet squares to match Room 4 2) Rooms 4 and 5: after removal of suspended ceiling (which museum staff could do) and paint exposed ceiling matte black to match the other museum gallery painted ceilings 3) Hallways: paint suspended ceiling tiles matte black to match other museum gallery ceilings Base Estimate & Alternates: $198,596.91 02/09/2023
Arts & Science Building - Renovate Various Rooms for Visual Studies (CP212061) Renovate rooms for occupancy by School of Visual Studies Digital Storytelling and Film areas. Base Estimate & Alternates: $260,000.00 02/13/2023