Planning, Design & Construction

Bid Opening Alert

Bid opening will be delayed for 24 hours if Campus is closed at 8:00 am on day of bid opening.
Check campus status at https://mualert.missouri.edu

Advertisements (Current, Upcoming, and Recent)

Combined Design/Bid/Build Projects

The following is a list of Design/Bid/Build projects bidding together. Click for project information.

Project Name (Project#) Prebid Meeting Date Bid Open Date Pre-Bid
Attendance
None at this time

Design/Bid/Build

The following is a list of construction projects out for bid. Click for project information.

Project Name (Project#) Prebid Meeting Date Bid Open Date
No Projects currently out for Bid.

Design/Bid/Build Projects for Prequalified Health Care Contractors

Click here for a list of the General Contractors that have been prequalified for the following projects:

Project Name (Project#) Prebid Meeting Date Bid Open Date
No Projects currently out for Bid.

Construction Manager at Risk

The following is a list of Construction Manager at Risk projects out for bid.

Project Name (Project#) Submission
Due Date
None at this time

Recently Opened Bids

The following is a list of bid projects opened in the last 30 days. Awarded contracts will appear in the "Recently Awarded Contracts" section

Project Name (Project #) Date
Bid
Opened
Bid
Tabulation
Green Tennis Facility — Structural Repairs (CP231391) 9/26/2023
Power Plant — Haul Road Repair (CP232791) 9/13/2023

Recently Awarded Contracts

The following is a list of recently awarded construction projects.

Project Name (Project #) Date
Contract
Awarded
Contract Awarded To Amount Awarded
Power Plant — Haul Road Repair (CP232791) 09/22/2023 EMERY SAPP & SONS $139,534.00
4011 Discovery Drive — Replace Chillers (CP230811) 09/12/2023 ENVIRONMENTAL ENGINEERING, INC. $871,500.00

Projects in Design

The following is a list of future construction projects.

Project Number, Title, and Scope
Est. Ad
Date
Est. Bid
Open
Date
Hill Hall - Building Envelope Repairs (CP220951) Remove existing wood windows and update with new aluminum windows. Patch and repair masonry as needed, tuckpointing of masonry facade along with installation/repair of front steps. Base Estimate & Alternates: $1,935,000.00 10/18/2023 11/08/2023
General Site - Tiger Avenue Roundabout Monument Signage (CP210048) Tiger Ave-Hospital Drive Monument Signage Base Estimate & Alternates: $472,172.00 10/20/2023
Laboratory for Infectious Disease Research - Renovate West Animal Holding, Rms 144-149 (CP220692) Convert our west animal holding suite to open-housing capable, including necessary addition of anteroom, shower, and HVAC modification Base Estimate & Alternates: $2,217,783.00 10/25/2023 11/08/2023
South Farm Swine Research & Education Facility - Construct Addition (CP230851) Construct a 12,000 square foot addition to the Swine Research Facility at South Farm. The existing building is approximately 14,000 gross square feet and comprised primarily of animal holding space. Base Estimate & Alternates: $3,917,514.00 11/01/2023 11/30/2023
Animal Science Research Center - Replace Electrical Service Entrance Panels (CP221041) Replace electrical Service Entrance Panels Base Estimate & Alternates: $1,236,384.00 11/21/2023 12/07/2023
General Site - Culvert Under Capen Park Drive Replacement (CP232061) Replacement of the Capen Park Drive storm sewer crossing. The storm sewer is nearing the end of its design life and will require replacement. The replacement of the storm sewer crossing will provide the highest level of protection for the Rock Quarry Surplus Warehouse. Replacement of the Capen Park Drive storm sewer crossing. The storm sewer is nearing the end of its design life and will require replacement. The replacement of the storm sewer crossing will provide the highest level of protection for the Rock Quarry Surplus Warehouse. Base Estimate & Alternates: $106,000.00 11/23/2023 12/12/2023
Neff Hall - HVAC Upgrades - Phase 2 (CP231442) Project involves installation of Owner Provided DOAS unit and HVAC upgrade to the building that will improve the fresh air intake and heating/cooling for the building occupants. Allowing for the existing window units to be removed from the building. Base Estimate & Alternates: $708,480.00 11/24/2023 12/22/2023
Hill Hall - AHU and Fire Alarm Systems Update, Phase 1 (CP222891) Replace ventilation systems and Fire alarm systems in this building in association with CP220951. Hill Hall HVAC system currently is AHU's above ceiling on each level's corridor ends, serving cold air and ventilation (through stairwells). These units are past end-of-life and freeze up their coils and the adjacent stairwells in the wintertime. They require a new way to deliver ventilation. A preliminary study has identified placing new units in the Attic as a solution. Fresh air will be acquired through roof penetrations (likely new dormers, facing west) and supply duct routed down through each floor to tie back into existing air handlers. This will require coordination between HVAC engineers, architects, and structural engineers to design safe and aesthetic renovations to the building to deliver code-compliant ventilation. The fire alarm system is dated and requires replacement at this time as well. A fire sprinkler water entrance will be added as well. Base Estimate & Alternates: $5,700,000.00 11/29/2023 01/03/2024
Student Recreation Center - AHU 1-3 Replacements (CP230262) Completely replace PAU-1/2/3 in the east mechanical room. Modify ductwork and piping (mostly within the east mechanical room) to support the new units in a slightly adjusted location. Provide new rooftop-mounted intake filters and heat recovery coils for each PAU due to insufficient space in mechanical room. Provide new rooftop relief fans to serve PAU-1/2/3. Provide 1x heat pump per PAU for energy recovery between the outdoor air and relief air streams. Same caveat as in Phase 1 regarding the economics. Base Estimate & Alternates: $2,775,000.00 11/29/2023 01/04/2024
Rock Quarry Surplus Warehouse - Paving Replacement (CP221442) Replace paving at Rock Quarry Surplus Warehouse Base Estimate & Alternates: $400,000.00 12/05/2023 12/21/2023
Hill Hall - Transformer Relocation (CP220952) Removal of the existing transformers beneath the stairs of Hill Hall and place a new transformer on a concrete pad on an exterior location. Base Estimate & Alternates: $35,000.00 12/12/2023 01/09/2024
Francis Quadrangle - Steam Tunnel & Sanitary Main Replacements (CP232811) Replace steam tunnel and sanitary main on the north side of Jesse Hall. Complete storm drainage improvements for the Quad sidewalks. Base Estimate & Alternates: $2,000,000.00 12/14/2023 01/18/2024
Schweitzer Hall - Roof Replacement (CP231262) Remove and replace the roof at Schweitzer Hall including RAD Remediation ? The work will include removal of the existing roofing materials/assemblies down to the roof decking ? The project will include replacement in-kind for each roofing assembly including tuck-pointing repair of brick chimneys, removal and resetting of cap and coping stones, and copper flashings. ? Removal and replace multiple exhaust fans housed within the attic and replace with centralized, roof mounted exhaust [strobic]. ? We are anticipating a potential for the replacement of 20% of the roof decking. ? We are anticipating limited structural repair of roof rafters on the west gable roof structure near the middle of the building. Base Estimate & Alternates: TBD 01/02/2024
National Swine Research and Resource Center - Construct Addition (CP230841) Construct an expansion of 12,220 gross square feet to the National Swine Research and Resource Center (NSRRC), a research animal housing and breeding facility. Base Estimate & Alternates: $5,917,254.00 01/08/2024 02/06/2024
Middlebush Farm - NextGen Center for Influenza Research - Phase II (CP230831) Phase Il is intended to enhance the overall BSL-2 animal capacity and increase throughput of research studies in influenza and emerging infectious diseases. This will be accomplished by focusing on more traditionally controlled animal holding spaces at lower cost per square foot due to the less intensive mechanical and electrical systems. A construction cost budget of approximately $5,000,000 is the target (project cost of $7.5M) will drive the final program. SEE Attachment Base Estimate & Alternates: $5,350,000.00 01/17/2024 02/28/2024
South Farm - Creed Barn Remodel (CP241191) A remodel of the Creed Building at the MU Beef Farm that includes renovation of an existing pole barn that will install a concrete floor with drains for a washdown of the area. Spray foam insulation on the walls and ceilings along with metal or wood wall covering for protection from the cattle. Electrical will need to be updated to include new LED lighting and electrical to accommodate an outlet for a storage area and general barn use. An alternative would look at adding an exhaust fan and radiant heater to provide minimal heating and cooling of the area. The client group will work to procure chutes and pins for a cattle processing area. Base Estimate & Alternates: $390,000.00 01/17/2024 02/14/2024
Physics Building - Replace Secondary Electrical Distribution and Service Entrance Panels (CP230551) Replace Secondary Electrical Distribution and Service Entrance Panels Base Estimate & Alternates: $600,000.00 03/29/2024 04/19/2024
General Site - Electric Interconnection and Substation (CP231541) General Site - Electric Interconnection and Substation Base Estimate & Alternates: $27,411,689.00 04/16/2024 05/29/2024
Hill Hall - AHU and Fire Alarm Systems Update, Phase 2 (CP222892) Replace ventilation systems and Fire alarm systems in this building in association with CP220951. Hill Hall HVAC system currently is AHU's above ceiling on each level's corridor ends, serving cold air and ventilation (through stairwells). These units are past end-of-life and freeze up their coils and the adjacent stairwells in the wintertime. They require a new way to deliver ventilation. Base Estimate & Alternates: TBD 05/31/2024 06/28/2024

Disclosure: This list is intended for information purposes only. This is not a complete list, nor is the information provided guaranteed to be correct. Stated dates are subject to change.

Design/Bid/Build Projects for Prequalified Health Care Contractors in Design

The following is a list of future construction projects.

Project Number, Title, and Scope
Est. Ad
Date
Est. Bid
Open
Date
University of Missouri Teaching Hospital - 3E44 Hybrid OR Installation (CP220871) Design for architectural and infrastructure updates needed to accommodate new hybrid OR equipment in an existing OR. Design in FY22 with Construction in FY23 Siemens Roadmap ID031 Base Estimate & Alternates: $838,745.71 10/30/2023
Patient Care Tower - 8th Floor BMT Phase 1B (CP221933) The project includes providing architectural, interiors, structural engineering, and MEPFP engineering support for design of a Bone Marrow Transplant Unit. Base Estimate & Alternates: $1,562,114.00 03/05/2024 03/26/2024

Disclosure: This list is intended for information purposes only. This is not a complete list, nor is the information provided guaranteed to be correct. Stated dates are subject to change.

MCA (Master Construction Agreement) Projects in Design

The following is a list of projects being made available through Nabholz. If you are interested in any of these projects, please contact Garett Plotts with Nabholz at Garett.plotts@nabholz.com.

Project Number, Title, and Scope
Est. Ad
Date
Horticulture Farm Agroforestry Education & Research Center - New Building Shell (CP221551) 4,920 square foot wood-framed building shell for the future build-out of interior conference and office space. Base Estimate & Alternates: $797,415.00 09/06/2023
Critical Care Addition - C2002G Symbia EVO Camera Installation (CP232231) Project to replace outdated and unserviceable Nuc-Med camera at UH. Base Estimate & Alternates: $263,823.75 09/19/2023
Tucker Hall - Suite 303 & 304 Renovations (CP231162) Renovate lab space for new faculty member. Previous lab design was completed in 2019 (CP191841) Base Estimate & Alternates: $700,309.00 09/28/2023
Jesse Hall - Auditorium Dimmer System Replacement (CP232651) Replace Dimmer System in Auditorium. Base Estimate & Alternates: $260,000.00 10/09/2023
Devine Athletic Pavilion - Facility Upgrades (CP233061) Project is to replace synthetic field turf [under an ICA contract], paint interior and roof structure, installation large fans and electrical for new netting. Base Estimate & Alternates: $735,000.00 10/11/2023
MU Research Reactor - Replace Corridor Flooring (CP232271) MURR is looking to apply epoxy to west-half of the building to match the east half Base Estimate & Alternates: $115,000.00 10/12/2023
University Hall - Suite 215 Office Renovation (CP232921) Renovate the back portion of Suite 215 to create an open concept office. Base Estimate & Alternates: TBD 10/16/2023
University Hall - Suite 225 Office Renovation (CP232931) Two Phase Project: Phase 1: Sub-divide room 226 into 4 offices. Furniture from other offices within the building are to be reused in new offices. New finishes are limited and only to be applied as necessary. Phase 2: Install new sprinkler system throughout second floor. Base Estimate & Alternates: TBD 10/23/2023
Bond Life Sciences Center - Breakroom Furniture (CP231741) East/West Wing First Floor 1st floor West, 2nd floor East/West wings, 3rd floor East/West wings, 4th floor East/West wings, 5th floor East wing Description of work: Remodel and/or replace current break room/kitchenette areas furniture located on the East and West wings of each corridor. The total amount of break room areas being remodeled would be 15 areas. Base Estimate & Alternates: TBD 10/25/2023
Clark Hall - 5th and 7th Floor Office Renovations (CP232741) Various 5th and 7th floor office-level renovations for the School of Social Work. Base Estimate & Alternates: TBD 11/01/2023
Stewart Hall - Renovate Rms 235 & 228 (CP231781) Scope: Renovate and subdivide room 235 for shared biology teaching classroom and lab prep room space. Renovate existing lab prep room 228 as needed to accommodate shared equipment and for storage. Base Estimate & Alternates: $135,759.83 12/04/2023
South Farm - Seed Cleaning Facility Update (CP232211) Upgrade the seed cleaning facility at Missouri Foundation Seed with modern machines and technology to meet the standards needed for Foundation Seed. Equipment is being procured by the Owner with installation by a contractor. Work to the facility will include demolition of the existing equipment and electrical, with a salvage portion for the electrical panels. New construction will consist of metal wall panels, roofing repair, electrical and controls work along with necessary site concrete and foundations. Additionally, the site electrical will need to be replaced with a new transformer and underground electrical service. Base Estimate & Alternates: $760,000.00 12/08/2023